What is the deadline for having an automatic line leak detector installed for underground pressurized product piping?

  1. July 1, 2003

  2. November 9, 2004

  3. July 1, 2004

  4. July 1, 1987

The correct answer is: November 9, 2004

The correct answer indicates that the deadline for having an automatic line leak detector installed for underground pressurized product piping was November 9, 2004. This requirement is part of compliance with regulations aimed at preventing environmental contamination from petroleum products due to leaks in underground storage systems. The date is significant because it reflects a critical milestone in regulatory standards to enhance safety measures in handling hazardous materials. As technology evolves, regulations typically respond to the need for improved leak detection systems to mitigate risks associated with fuel leaks. Working within the context of safety and environmental regulations, understanding these deadlines is essential for UST (Underground Storage Tank) operators and inspectors. Properly installed leak detection equipment is crucial for monitoring the integrity of pressurized piping systems, thereby ensuring compliance with regulatory requirements designed to protect public health and the environment. Earlier dates in the choices represent previous regulatory updates but do not reflect the specific deadline for automatic line leak detectors as mandated for compliance, highlighting the evolution of regulatory frameworks leading up to 2004.